EXAM PSP QUESTIONS PDF & PSP EXAM DUMPS COLLECTION

Exam PSP Questions Pdf & PSP Exam Dumps Collection

Exam PSP Questions Pdf & PSP Exam Dumps Collection

Blog Article

Tags: Exam PSP Questions Pdf, PSP Exam Dumps Collection, PSP Valid Dump, Valid Dumps PSP Book, PSP Test Questions Answers

P.S. Free & New PSP dumps are available on Google Drive shared by Fast2test: https://drive.google.com/open?id=1gM4NuNCT6iq_B_7brwoXEUI1D0gcLPuL

As you know, opportunities are reserved for those who are prepared. Everyone wants to stand out in such a competitive environment, but they don't know how to act. Maybe our ASIS Physical Security Professional Exam exam questions can help you. Having a certificate may be something you have always dreamed of, because it can prove that you have a certain capacity. Our learning materials can provide you with meticulous help and help you get your certificate. Our PSP training prep is credible and their quality can stand the test. Therefore, our practice materials can help you get a great financial return in the future and you will have a good quality of life.

ASIS PSP Certification Exam covers a range of topics related to physical security, including security principles and practices, physical security assessments, security system design, and emergency response planning. Candidates must demonstrate a thorough understanding of these topics through a rigorous exam that tests their knowledge, skills, and experience. ASIS Physical Security Professional Exam certification is valid for three years and requires ongoing professional development to maintain. Overall, the ASIS PSP Certification Exam is an essential certification for professionals in the field of physical security and offers a valuable opportunity for career advancement and professional growth.

ASIS PSP (ASIS Physical Security Professional) Exam is a globally recognized certification program designed to assess and validate the knowledge and skills of professionals in the physical security industry. ASIS Physical Security Professional Exam certification is offered by ASIS International, a professional organization that provides education, networking opportunities, and advocacy for security professionals worldwide.

ASIS PSP (Physical Security Professional) certification exam is one of the most prestigious security-focused professional certifications in the world. ASIS Physical Security Professional Exam certification is designed to test the knowledge and expertise of security professionals in the areas of physical security, risk assessment, and threat management. The ASIS PSP certification exam is a rigorous test that requires professionals to have a deep understanding of the principles and practices of physical security, as well as the ability to apply that knowledge to real-world situations.

>> Exam PSP Questions Pdf <<

First-rank PSP Practice Materials Stand for Perfect Exam Dumps - Fast2test

We are pleased to inform you that we have engaged in this business for over ten years with our ASIS Physical Security Professional Exam PSP exam questions. Because of our experience, we are well qualified to take care of your worried about the PSP Preparation exam and smooth your process with successful passing results.

ASIS Physical Security Professional Exam Sample Questions (Q140-Q145):

NEW QUESTION # 140
Assuming conventional finish-to-start relationships, to calculate a schedule retaining the existing logic means that

  • A. It is calculated using the original logic.
  • B. There is no such thing.
  • C. It is calculated using logic reflecting out-of-sequence progress.
  • D. An out-of-sequence activity cannot resume until all predecessors are finished.

Answer: A

Explanation:
Retaining existing logic means preserving the original relationships and dependencies defined in the schedule.
Even if progress is recorded out of sequence, calculations adhere to the pre-established logic unless explicitly changed.
* Option B reflects adjustments for out-of-sequence progress but contradicts the original logic requirement.
* Option C imposes restrictions that do not align with typical CPM calculations.
* Option D is incorrect as the concept exists.
The PSP Study Guide discusses the importance of maintaining logic integrity in CPM scheduling.


NEW QUESTION # 141
Using the "normal" schedule, theoretically construct a hammock for activities 6001-6003. What is the duration of the hammock?

  • A. 362 days
  • B. 407 days
  • C. 267 days
  • D. 255 days

Answer: A

Explanation:
Understand the Concept of a Hammock Activity:
* A hammock activity spans over multiple activities and reflects the cumulative duration from the earliest start to the latest finish of the grouped activities.
Activities in the Hammock (6001-6003):
* Activity 6001: Duration = 102 days, FS relationship with successor.
* Activity 6002: Duration = 140 days, FS with 6001.
* Activity 6003: Duration = 115 days, FS with 6002.
Calculate the Duration:
* Earliest Start of Activity 6001 # Latest Finish of Activity 6003.
* Total duration = 102 + 140 + 115 = 362 days.
Cross-Verification with Answer Options:
* Option A: Incorrect. Overestimates.
* Option C: Incorrect. Underestimates.
* Option D: Incorrect. Underestimates.
* Option B: Correct. Matches the calculated duration.


NEW QUESTION # 142
In the normal schedule, excluding Activity 1000. what activity(s) are concurrent with Activity 3001?

  • A. 2003 and 7001
  • B. 4001 and 5001
  • C. 4001, 5001, and 6001
  • D. 2004, 4001. and 5001

Answer: C


NEW QUESTION # 143
Using the "normal" schedule, given Activity 3001 and the relationship with Activity 4001, what is indicated?

  • A. The activities occur in series with a 15-day lag.
  • B. These activities are concurrent with Activity 4001 starting 15 days earlier than the start of Activity 3001.
  • C. The activities run concurrently.
  • D. These activities are concurrent with Activity 4001 starting 15 days after the start of Activity 3001.

Answer: D

Explanation:
* Analyze the Relationship Details:The table shows that Activity 3001 ("Excavation, Dam Site") and Activity 4001 ("Excavation, Spillway") have a Start-to-Start (SS) relationship with a lag of 15 days. A Start-to-Start relationship indicates that the successor activity (4001) can only start after a specified lag period once the predecessor activity (3001) begins.
* Understand the Concept of Lag:In scheduling terminology, lag refers to a delay or waiting period between the start (or finish) of one activity and the start (or finish) of a dependent activity. Here, the 15- day lag means that Activity 4001 will commence 15 days after Activity 3001 has started.
* Interpret the Relationship:The SS relationship combined with a lag indicates that the two activities (3001 and 4001) are not starting exactly at the same time but are still overlapping or concurrent. This concurrency happens after the lag period elapses.
* Verify PSP Study Guide and Relevant Terminology:According to AACE International's Recommended Practices and the PSP Certification Study Guide:
* Start-to-Start relationships are widely used to model overlapping work in schedules where one activity can start before its predecessor is fully complete (PSP Study Guide, Chapter on Scheduling Relationships and Constraints).
* Lags provide flexibility to model realistic conditions where tasks start partially overlapping or with delays (PSP Study Guide, Section 2.2.4 Relationships).
* Cross-Check the Answer Options:
* Option A (Correct): Matches the described logic - "These activities are concurrent with Activity
4001 starting 15 days after the start of Activity 3001."
* Option B: Incorrect - Lag is applied to the successor activity, meaning 4001 cannot start earlier than 3001.
* Option C: Incorrect - This relationship (SS with a lag) indicates concurrency, not series.
* Option D: Incorrect - Though concurrent, the lag makes the start times offset by 15 days, so they do not start at the same time.
References:
* PSP Study Guide (2019), Chapter 2A - Schedule Development, Section 2.2.4 - Relationships.
* AACE International Recommended Practices, RP 10S-90, "Cost Engineering Terminology."
* Total Cost Management Framework, Concepts of Activity Relationships and Scheduling Dependencies.


NEW QUESTION # 144
Determine the correct formula and date for the late finish for Activity 9004.